U.S. 50 Phase 2 Widening Project

Print
Press Enter to show all options, press Tab go to next option

Project Description

A road photo along US 50 from Stagecoach to SilverspringsThe U.S. 50 Phase 2 widening project adds a key link to one of the most traveled corridors in Lyon County. The project will help reduce crashes, increase safety for the traveling public, provide connectivity and mobility by designing concrete High-T intersections at county roads. Adding these elements on U.S. 50 will help control access to provide safety to the travelling public, which is similar to the U.S. 50 Phase 1 Project.

The scope of the project is to design and construct a new four-lane divided highway which will connect to the previously-constructed Phase 1 widening project. The project will begin at Roys Road and end at the junction of U.S. 50 and U.S. 95A in Silver Springs. The design will also consist of intersection lighting, drainage improvements, and signage.

Other Project Benefits

  • Replacing the stop condition at U.S. 50 and U.S. 95A in Silver Springs with a new single lane concrete roundabout
  • Extending the US 95A northbound truck climbing lane 
  • Landscape and Aesthetics improvements
  • Connection to the existing USA Parkway roundabout
  • New fencing and cattle guards to control wildlife from entering the new corridor
  • Frontage road connection to county roads
  • Utility coordination

NDOT is delivering the project via the traditional design-bid-build method, with the design conducted by NDOT’s professional engineers and construction by Granite Construction. Construction started in January 2019 and is expected to be complete by fall 2020.

A graphic of a 55 mile per hour speed limit signConstruction Updates and Traffic Control

Through November, both directions of traffic on U.S. 50 will be shifted to new westbound lanes from Roy’s Road in Stagecoach to near the U.S. 50/U.S. 95A junction in Silver Springs.

The speed limit will be reduced from 65 mph to 55 mph on U.S. 50 within the project limits for the foreseeable future during construction. 

Fully-paved one-way frontage roads have been constructed on the outside of the U.S. 50/U.S. 95A intersection in Silver Springs. Motorists will drive the frontage roads in a counterclockwise direction, making right-hand turns to access roads and businesses in the same manner as a traffic roundabout. Speed limits will be reduced to 20 mph on the frontage roads.

The temporary detour is scheduled to be in place through the end of the year as a permanent roundabout is installed to replace the existing flashing traffic signal at the junction. The concrete roundabout will make intersection travel safer and quicker, with free right turns between U.S. 50 and southern U.S. 95 Alternate. Roundabouts can reduce fatal and serious injury crashes by up to 87%.

Project Timeline

  • Final design completed: fall 2018
  • Construction start: beginning 2019
  • Construction completion: fall 2020

Where Are We?

Crews have thus far excavated and paved approximately nine miles of new westbound lanes. 

Through late 2019, construction work will focus on installing the new roundabout at U.S. 50 and U.S. 95A and paving the new eastbound lanes.

Westbound US 50 Looking EastWestbound US 50 Looking WestWestbound US 50 Looking West

Project Funding

The U.S. 50 Phase 2 Widening Project is funded by federal and state funding. The estimated construction cost is $55 million.

Videos

 

 

Resources

Safety and Operational Improvements

Contact

For more information regarding the U.S. 50 Widening Project, email requests to: publicrecordsreq@dot.nv.gov.