> New US-95/I-15 High-Occupancy Vehicle (HOV) lanes, including the Spaghetti Bowl flyover, Opened in Las Vegas on May 20th. {Click for HOV Do’s & Don’ts}

> The next blasting along SR-160 thru Mountain Springs in Clark County will occur on Tuesday, June 18th at 11:45 a.m. Expect delays up to 2 hours.

[Click Here for More Road Information]

News Releases

Print
Press Enter to show all options, press Tab go to next option
 
searchsettings

I-15 Northbound Weekend Closure

Sahara Ave to D Street

Post Date:06/12/2019 12:55 PM

I-15 Northbound Weekend Closure
Sahara Ave to D Street


Las Vegas, Nev. – Between 10 p.m. Friday, June 14 and 5 a.m. Monday, June 17, northbound I-15 will be closed between Sahara Avenue and D Street, as Project Neon repaving and restriping operations continue, according to the Nevada Department of Transportation (NDOT).

The following ramps will also be closed:

 

From 8 p.m. on Friday, June 14 to 6 a.m. on Monday, June 17:

  • Sahara Ave on-ramp to I-15 northbound

  • Charleston Blvd on-ramp to I-15 northbound

  • Neon Gateway HOV on-ramp to I-15 northbound

  • MLK Blvd on-ramp to I-15 northbound

  • MLK Blvd on-ramp to US 95 northbound

 

From 9 p.m. on Friday, June 14 to 6 a.m. on Monday, June 17:

  • US 95 southbound to I-15 northbound

 

From 10 p.m. on Friday, June 14 to 5 a.m. on Monday, June 17:

  • I-15 northbound to US 95 northbound

  • I-15 northbound to US 95 southbound

  • HOV flyover from I-15 northbound to US 95 northbound

 

Crews are applying a special crumb rubber asphalt mix, incorporating shredded tires for a smoother, quieter ride. The recycled tire material also lasts twice as long as traditional asphalt pavement while creating a better fraction surface during adverse weather conditions.

Motorists are strongly encouraged to use alternate routes during this closure. The 215 Beltway and US 95 are good options to avoid the closure. To access US 95 northbound, consider north/south streets west of I-15. To access US 95 southbound, consider north/south streets east of I-15. NDOT works with the Waze app to inform the public about construction and suggested detours.

Project Neon is 96 percent finish with substantial completion scheduled by mid-July.

For additional information, check the Project Neon website (NDOTProjectNeon.com), Facebook, LinkedIn or Twitter pages (@NDOTProjectNeon).

 

###