Construction, Construction Read All About It!
In cooperation with all Counterpart agencies, this edition of the Counterparts newsletter is dedicated to
keep everyone informed of the upcoming 2009 construction season activities. Due to the sheer volume of
work that will be taking place in the Tahoe Basin in 2009, we realize that the upcoming construction
season will be busy and create challenges for Tahoe travelers as there will be numerous projects
constructed concurrently throughout the California and Nevada sides of the Basin.
Many of the projects presented are associated with Caltrans’ and NDOT’s Lake Tahoe Environmental Improvement Programs (EIP), and together we are committed to providing better and safer roads in addition to protecting the environment. We understand the frustrations people face as they are traveling through construction zone after construction zone, as we are travelers too; however, providing early notice of these construction projects should help to ease your frustrations.
Over the years, all Counterpart agencies have been working cooperatively to enhance, maintain and protect the natural environment of Lake Tahoe and at the same time provide safer roadways. Consequently, very necessary projects include repairing pot holes and damaged roadways, performing source and erosion control to keep sediments and other pollutants from entering the lake, placing new and re-placing damaged barrier rail and guardrail, installing dynamic message signs as well as advisory radio systems to help get information out to the traveling public, etc.
Download the 2009 Tahoe Basin Construction Map. (1.7 MB).
| Contacts regarding projects: | ||
|
Nevada Department of Transportation(NDOT) All Counties Scott Magruder (775) 888-7777 |
California Department of Transportation(CALTRANS) Placer County (PLA) and El Dorado County (ED) Rochelle Jenkins (530) 634-7640 |
|
2009 Tahoe Basin Construction Activities
* Expect Delays| U.S. Interstate 80 |
|
Project 1* Where: Pla-80 PM 66.3 - 68.5 Interstate 80 Near Kingvale What: Concrete Rehabilitation When: 2007 - 2009 Up to 30 Minute Delay, Night Work |
|
Project 2* Where: Nev-80 PM R2.3 - R5.7 Interstate 80 Near Donner Summit What: Concrete Rehabilitation When: 2007 - 2009 Up to 30 Minute Delay, Night Work |
|
Project 3* Where: Nev-80 PM R5.6 - R11.5 Interstate 80 Near Truckee What: Concrete Rehabilitation When: 2009 - 2011 Up to 30 Minute Delay, Night Work |
|
Project 4* Where: Nev-80 PM R9.2 - R13.6 Interstate 80 Donner Lake Undercrossing What: PCC Overlay When: 2009 - 2010 Up to 30 Minute Delay, Night Work |
|
Project 5* Where: Nev-80 - PM 27.5 What: County Bridge Replacement, one lane open WB on/off ramp When: May - Oct. 2009 Up to 15 Minute Delay |
|
Project 6* Where: Nev, Sie-80 - PM 28.1/31.8 Interstate 80 Near Floriston to State Line What: Roadway Rehabilitation When: 2009 - 2011. Up to 30 Minute Delay, Night Work |
| California State Route 89 |
|
Project 7* Where: Pla-89 PM 8.6/13.7 Junction 89/28 to Squaw Valley Rd. What: Water Quality Improvement When: 2009 - 2010 Up to 30 Minute Delay, Night Work |
|
Project 8* Where: Pla-89 PM 8.1-8.3 State Route 89 W. Lake Blvd. What: Transit Center Parking Lot When: May - Oct. 2009 Up to 15 Minute Delay |
|
Project 9* Where: Pla-89 PM 0.0/8.5 State Route 89 W. Lake Blvd. What: Gateway Monument/Water Quality Improvement When: May - Oct. 2009 Up to 15 Minute Delay |
| California State Route 267 |
|
Project 10* Where: Pla-267 PM 8.7/9.9 Junction 267/28 to Stewart Way What: Water Quality Improvement When: 2009 - 2010 Up to 30 Minute Delay, Night Work |
|
Project 11* Where: Pla-267 PM 0.0 - 0.1 State Route 267 What: Highway Access to Commercial Development When: May - Oct. 2009 Up to 15 Minute Delay |
| California State Route 28 |
|
Project 12* Where: Pla-28 PM 0.8/11.0 Tahoe State Park to State Route 267 What: Water Quality Improvement When: 2009 - 2010 Up to 30 Minute Delay, Night Work |
| Nevada State Route 28 |
|
Project 13* Where: PM DO 0.00 to WA 5.29 State Route 28 from the Junction of U.S. 50 Near Spooner Summit to Ponderosa Ranch What: Rehabilitation of Existing Roadway When: |
|
Where: Sand Harbor - Nevada State Park What: Roadway Resurfacing When: June - September 2009 Nightly Closure |
| Nevada State Route 207 |
|
Project 14* Where: PM DO 0.00 to DO 3.14 State Route 207 Kingsbury Grade from Junction of 50 Near Dagget Pass What: Replacement of Existing Drainage, Retaining Wall and Repair Crib Wall When: June 2009 - Oct. 2011 Up to 30 Minute Delay |
| U.S. Highway 50 |
|
Project 15* Where: ED-50 PM 66.8/69.3 Near Echo Lake What: Install Netting for Slope Protection When: Sept. - Oct. 2009 Up to 15 Minute Delay |
|
Project 16 * Where: ED-50 PM 74.7-80.4 U.S. 50 to Nevada State Line What: Micro Surfacing and Traffic Improvement When: April - Aug. 2009 Up to 15 Minute Delay |
|
Project 17* Where: ED-50 PM 77.2/79.8 U.S. 50 Lake Tahoe Blvd. What: Relocate 8” Gas Main When: April - June 2009 Up to 10 Minute Delay |
|
Project 18* Where: ED-50 PM 80.1-80.3 U.S. Park Ave. to State Line What: Service/Pothole/Modify When: April - Oct. 2009 Up to 15 Minute Delay |
|
Where: ED, Pla - Various Locations U.S. 50, SR 89 and 28 What: Install Traffic Operation System When: April - July 2009 Up to 15 Minute Delay |
|
Where: Cave Rock Boat Landing - Nevada State Park What: Roadway Resurfacing When: June - September 2009 Nightly Closure. |