Tahoe Basin Construction


Construction, Construction Read All About It!

Lake Tahoe Shoulder Work In cooperation with all Counterpart agencies, this edition of the Counterparts newsletter is dedicated to keep everyone informed of the upcoming 2008 construction season activities. Due to the sheer volume of work that will be taking place in the Tahoe Basin in 2008, we realize that the upcoming construction season will be busy and create challenges for Tahoe travelers as there will be numerous projects constructed concurrently throughout the California and Nevada sides of the Basin.

Many of the projects presented are associated with Caltrans’ and NDOT’s Lake Tahoe Environmental Improvement Programs (EIP), and together we are committed to providing better and safer roads in addition to protecting the environment. We understand the frustrations people face as they are traveling through construction zone after construction zone, as we are travelers too; however, providing early notice of these construction projects should help to ease your frustrations.

Over the years, all Counterpart agencies have been working cooperatively to enhance, maintain and protect the natural environment of Lake Tahoe and at the same time provide safer roadways. Consequently in 2008, upcoming and very necessary projects will include repairing pot holes and damaged roadways, performing source and erosion control to keep sediments and other pollutants from entering the lake, placing new and re-placing damaged barrier rail and guardrail, installing dynamic message signs as well as advisory radio systems to help get information out to the traveling public, etc.

Download the 2008 Tahoe Basin Construction Activities Map and Key. (219 kB).

Contacts regarding projects:
Nevada Department of Transportation(NDOT)
All Counties
Scott Magruder
(775) 888-7777
California Department of Transportation(CALTRANS)
Placer County (PLA) and El Dorado County (ED)
Shelly Chernicki
(530) 741-5474

2008 Tahoe Basin Construction Activities

California and Nevada State Route 28
Project 1*
Where: SR 28 (Caltrans) Tahoe State Park to SR 267
What: Water Quality Improvements
When: 2008 - 2012. Up to 30-minute delay, night work

Project 2*
Where: CSR 28 (Caltrans) Chipmunk St. to Nevada State Line
What: Water Quality Improvements
When: 2008 - 2012. Up to 30-minute delay,night work

Project 3*
Where: SR 28 (IVGID) At the Douglas County Line
What: Construct 250' of 16-inch pipeline in NDOT R/W (southbound lane)
When: April, 2008 - June, 2008. Up to 20-minute delay,night work allowed

Project 4
Where: SR 28 Side Streets (Placer County) Stag Dr. to National Ave.
What: Water Quality Improvements
When: May, 2008 - September, 2008.

Project 5
Where: SR 28 Side Streets (Placer County) Dollar Dr. to Lakewood Ln.
What: Water Quality Improvements
When: July, 2008 - October, 2008.

Project 7*
Where: SR 28 (Washoe County) 330' North of Reservoir Dr. to Stateline
What: Underground Utilities
When: May, 2008 - September, 2008. Up to 10-minute delay

Project 8*
Where: SR 28 (Washoe County) Stateline to Islet Ave.
What: Underground Utilities
When: May, 2008 - September, 2008. Up to 10-minute delay


U.S. Highway 50
Project 9
Where: US 50 (NDOT) US 395 to Spooner Summit
What: Paving
When: April, 2008 - October, 2008. Day and Night work
Project 10
Where: US 50 (NDOT) Spooner Summit to Nevada Beach Rd.
What: Paving
When: April, 2008 - October, 2008. Day and Night work

Project 11*
Where: US 50 (IVGID) Spooner Summit to the Junction of US 50 and SR 28
What: Construct 4500' of 16-inch pipeline in NDOT R/W
When: April, 2008 – June 2008. Up to 20-minute delay. Night work allowed

Project 12*
Where: US 50 (City of South Lake Tahoe) Intersection of US 50 and SR 89
What: Lane Widening
When: May, 2008 – October 2008. Up to 30-minute delay

Project 13*
Where: US 50 (City of South Lake Tahoe) Stateline Ave to Park Ave.
What: Redevelopment: Streetscape Construction
When: May, 2008 – October 2008. Up to 10-minute delay

Project 14*
Where: US 50 (KGID) SR 207 to CA/NV Stateline
What: Edgwood/KGID Intertie Improvements
When: May, 2008 – November 2008. Up to 20-minute delay. Night work


U.S. Interstate 80
Project 15
Where: I-80 (NDOT) NV/CA Stateline to Robb Dr. Interchange
What: Paving
When: April, 2008 - August, 2008. Night work

Project 20*
Where: I-80 (CalTrans) CA/NV Stateline to Colfax. Various locations
What: Concrete overlay, rehab, widening.
When: April, 2008 - October, 2012


U.S. Interstate 580
Project 16
Where: I-580 (NDOT) Mount Rose Interchange to Bowers Mansion
What: New Construction
When: Spring, 2008 - Summer, 2011


California State Route 89
Project 17*
Where: SR 89 (Caltrans) Junction of SR89 & SR28 to Squaw Valley Rd.
What: Water Quality Improvements
When: 2008 - 2010. Up to 30-minute delay. Night work

Project 6
Where: SR 89 Side Streets (Placer County) Sequoia Ave. to Pine Ave.
What: Water Quality Improvements
When: May, 2008 - September, 2008.


Nevada State Route 207
Project 18*
Where: SR 207 Side Streets (KGID) Intersections of SR 207 &: Pine Ridge Dr., Cottonwood Dr., Meadow Ln., Juniper Dr., Chimney Rock Rd.
What: Road Sealing Intersections
When: July, 2008 - September, 2008. Up to 10-minute delay
Project 19*
Where: SR 207 Side Streets (KGID) at S.Benjamine Dr.
What: Road Sealing Intersections
When: July, 2008 - September, 2008. Up to 10-minute delay


* Expect Delays

You will need the Adobe Acrobat Reader plug-in to download and view the files on this site. If you don't have the plugin, you can download the plugin by clicking on the Get Acrobat Reader button here.

Get Adobe Acrobat Reader



1263 South Stewart Street, Carson City, Nevada 89712 - Telephone: 775-888-7000 - Fax: 775-888-7115 - Email: info@dot.state.nv.us
Copyright © 1998 - 2008 Nevada Department of Transportation
Valid HTML 4.01! Valid CSS!