FACT SHEET Contract 3167 US 95 Widening - Project 3A - SR-599 Rancho Drive Storm Drain


July 10, 2003
Contact: Bob Mckenzie
Phone: (702) 385-6504

FACT SHEET Contract 3167 US 95 Widening - Project 3A - SR-599 Rancho Drive Storm Drain

FACT SHEET
US 95 Widening - Project 3A
Contract 3167: SR-599 Rancho Drive Storm Drain

* Construct the Rancho Drive reinforced concrete box storm drain
* Rancho Drive between Mesquite Avenue (south of US 95) to Washington Avenue

Bid Information

Low Bid Determination = A + (B x Daily Cost)= $7,026,418.50
Where: A = Total Amount of Proposal $5,826,418.50
B = Established Working Day Number 120 Days
Daily Cost = ($10,000 X 120) = $1,200,000.00

The above formula was used solely for the purpose of determining the low bidder and has no effect on the actual total bid cost for completing the work.

* Bid Date: July 10, 2003
* Apparent Low Bidder: Las Vegas Paving Corporation, Las Vegas, NV
* Contract Bid Amount:: $5,826,418.50
* Project Start Date: TBD
* Project Duration: 120 working days

Project Phasing

Phase 1 – Utility Relocations
* Perform utility relocation evenings between 9:00 p.m. to 6:00 a.m.

Phase 2 – Median Island Removals
*Perform median removals and pavement reconstruction evenings between 9:00 p.m. and 6:00 a.m.
*Working days will be suspended after completion of Phase 1 and 2 until January 5, 2004.

Phase 3 – Construct Drainline “RL” and adjacent Rancho Drive Improvements
* Begin after January 5, 2004
* Includes construction of sanitary sewer relocation and deep sewer manhole

* Phase 3A Box-A-Thon
* Begin on a Friday evening at 9:00 and and last for no more than 249 consecutive hours
* Maintain minimum of one lane of travel in each direction on Rancho Drive
* Northbound US 95 off-ramp to Rancho Drive will be closed
* Southbound US 95 off-ramp to Rancho Drive will be limited to right turn only to access Rancho Drive
* No left turn from Rancho Drive to the US 95 on-ramps

* Phase 3B Construct Drainline Box-A-Thon
* Begin immediately following completion of 3A for no more that 192 consecutive hours
* Maintain minimum of one lane of travel in each direction on Rancho Drive
* No left turn from Rancho Drive to southbound US 95 on-ramp
* Northbound US 95 off-ramp to Rancho Drive will be closed
* Southbound US 95 off-ramp to Rancho Drive will be limited to right turn only to access Rancho Drive

* Phase 3C & D Construct Drainline
* Begin immediately following completion of 3B
* Pavement reconstruction and construction of adjacent curbs, drainage inlets, sidewalks and street lights
* Maintain minimum of two lanes of travel in each direction on Rancho Drive
* Additional lane may be taken in work zone between 9:00 p.m. and 6:00 a.m.

* Phase 3E Construct Southbound Rancho Drive Improvements
* Cold mill and paving operations eveneings between 9:00 p.m. and 6:00 a.m.
* Maintain minimum two northbound travel lanes and one southbound travel lane on Rancho Drive during evening hours
* Maintain two lanes of travel during daylight hours

Phase 4 A & B Construct drainlines and adjacent Washington Avenue Improvements
* Perform work evenings between 9:00 p.m. to 6:00 a.m.
* Maintain at least one lane of travel in each direction on Washington Avenue and Rancho Drive
* Restrict left turn movement from eastbound Washington Avenue to northbound Rancho Drive

Phase 4C Construct drainlines and adjacent Washington Avenue Improvements
* Cold mill intersection of Washington Avenue and Rancho Drive
* Perform work evenings between 9:00 p.m. to 6:00 a.m.