NDOT BID DOCUMENTS CHANGE TO PROVIDE BID RANGE
For all projects advertised after October 1, 2008, the Nevada Department of Transportation is now providing an estimated bid range instead of the detailed engineer’s estimate during the contract advertisement period.
Instead of the detailed engineer’s estimate that was previously provided, NDOT now provides a contract items list. This contract items list contains a detailed list of contract bid items and quantities. Instead of the total project dollar figure previously found in the engineer’s estimate, it gives an estimated contract bid range and not estimated unit prices.
This estimated project cost range is provided within NDOT bid documents, and the table of all cost ranges is available for reference on this page of the www.nevadadot.com Web site. A detailed engineer’s estimate is available during bid opening.
All other schedules, elements and requirements of the contract process will remain the same. For further information, contact NDOT Administrative Services at (775) 888-7070.
Bid Range available in PDF format
| Range # | Contract Cost Range |
| R1 | $0.00 to $10,000 |
| R2 | $10,000.01 to $50,000 |
| R3 | $50,000.01 to $100,000 |
| R4 | $100,000.01 to $120,000 |
| R5 | $120,000.01 to $145,000 |
| R6 | $145,000.01 to $175,000 |
| R7 | $175,000.01 to $205,000 |
| R8 | $205,000.01 to $250,000 |
| R9 | $250,000.01 to $300,000 |
| R10 | $300,000.01 to $360,000 |
| R11 | $360,000.01 to $430,000 |
| R12 | $430,000.01 to $515,000 |
| R13 | $515,000.01 to $620,000 |
| R14 | $620,000.01 to $745,000 |
| R15 | $745,000.01 to $890,000 |
| R16 | $890,000.01 to $1,050,000 |
| R17 | $1,050,000.01 to $1,300,000 |
| R18 | $1,300,000.01 to $1,550,000 |
| R19 | $1,550,000.01 to $1,850,000 |
| R20 | $1,850,000.01 to $2,200,000 |
| R21 | $2,200,000.01 to $2,650,000 |
| R22 | $2,650,000.01 to $3,200,000 |
| R23 | $3,200,000.01 to $3,850,000 |
| R24 | $3,850,000.01 to $4,600,000 |
| R25 | $4,600,000.01 to $5,500,000 |
| R26 | $5,500,000.01 to $6,600,000 |
| R27 | $6,600,000.01 to $7,950,000 |
| Range # | Contract Cost Range |
| R28 | $7,950,000.01 to $9,550,000 |
| R29 | $9,550,000.01 to $11,500,000 |
| R30 | $11,500,000.01 to $13,500,000 |
| R31 | $13,500,000.01 to $16,500,000 |
| R32 | $16,500,000.01 to $20,000,000 |
| R33 | $20,000,000.01 to $23,500,000 |
| R34 | $23,500,000.01 to $28,500,000 |
| R35 | $28,500,000.01 to $34,000,000 |
| R36 | $34,000,000.01 to $41,000,000 |
| R37 | $41,000,000.01 to $49,000,000 |
| R38 | $49,000,000.01 to $59,000,000 |
| R39 | $59,000,000.01 to $71,000,000 |
| R40 | $71,000,000.01 to $85,000,000 |
| R41 | $85,000,000.01 to $100,000,000 |
| R42 | $100,000,000.01 to $120,000,000 |
| R43 | $120,000,000.01 to $145,000,000 |
| R44 | $145,000,000.01 to $175,000,000 |
| R45 | $175,000,000.01 to $210,000,000 |
| R46 | $210,000,000.01 to $255,000,000 |
| R47 | $255,000,000.01 to $305,000,000 |
| R48 | $305,000,000.01 to $365,000,000 |
| R49 | $365,000,000.01 to $440,000,000 |
| R50 | $440,000,000.01 to $525,000,000 |
| R51 | $525,000,000.01 to $630,000,000 |
| R52 | $630,000,000.01 to $760,000,000 |
| R53 | $760,000,000.01 to $910,000,000 |
| R54 | $910,000,000.01 to $1,000,000,000 |